SC_wire Referenznummer der Bekanntmachung: 27/2600000882/20FAIR
Auftragsbekanntmachung
Lieferauftrag
Abschnitt I: Öffentlicher Auftraggeber
Postanschrift:[gelöscht]
Ort: Darmstadt
NUTS-Code: DE711 Darmstadt, Kreisfreie Stadt
Postleitzahl: 64291
Land: Deutschland
E-Mail: [gelöscht]
Telefon: [gelöscht]
Fax: [gelöscht]
Internet-Adresse(n):
Hauptadresse: http://www.fair-center.de
Abschnitt II: Gegenstand
SC_wire
Fast ramped superconducting magnets will be used for the SIS100 synchrotron
of FAIR. The low-loss superconducting strand needed to build the coils of these
magnets and Fast ramped superconducting corrector magnets as for example multipole correctors, chromaticity sextupoles and steering magnets are needed for the SIS100 synchrotron of FAIR. The insulated low-loss superconducting strand is needed to build the coils of these magnets.
FAIR - Facility for Antiproton and Ion Research in Europe GmbH Planckstr. 1 64291 Darmstadt
Production and Delivery of 380km Superconducting Strand for Main Magnets and 200km Superconducting Strand for Corrector Magnets according to the specifications.
Abschnitt III: Rechtliche, wirtschaftliche, finanzielle und technische Angaben
Supporting documents:
- 4. Self-declaration of suitability pursuant to Sections 123, 124 GWB (To be submitted with the tender by means of self-declaration): Self-declaration of possessing the knowledge pursuant to Sections 123, 124 GWB is incorrect and that the cases mentioned therein do not apply - FAIR preprinted form
- 5. Company presentation (To be submitted with the tender by means of self-declaration): With the information asked for on the FAIR preprinted form, the number of employees over the previous three years - on the FAIR preprinted form under Company presentation
Supporting documents:
- 6. Information on overall revenues and order-specific revenue (To be submitted with the tender by means of self-declaration): Declaration of the total company turnover and the turnover in relation to the particular type of service to which the award relates, in both cases, in relation to the last 3 financial years - on the FAIR preprinted form under Company presentation.
- 8.1 Proof of commercial liability insurance (To be submitted with the tender by means of self-declaration): Proof of a commercial liability insurance must be provided with the preprinted form.
Supporting documents:
- 10. Description of reference projects (To be submitted with the tender by means of self-declaration): Description of comparable reference projects, including the project data asked for on the FAIR preprinted form.
with the following minimum requirements for the references:
At least 2 references from the last 10 years which proof the following experience beyond doubt:
-Production of fine filament (2 - 5 Müm diameter) NbTi superconducting wires with CuMn interfilamentary matrix in great lengths (>350 km)
At least 1 reference from the last 10 years which proof the following experience beyond doubt:
-Polyimide enamel insulation of superconducting wire on big scale (>100 km). Isolation thickness needs to be on the range of 0.02 mm to 0.06 mm for wire diameters in the range of 0.5 mm to 1 mm.
Supporting documents:
- 1. Act Regulating a General Minimum Wage (MiLoG) (To be submitted with the tender by means of self-declaration): Declaration as per Section 19 (3) MiLoG - FAIR preprinted form
- 2. Proofs for subcontractors (To be submitted with the tender by means of self-declaration): The name and address of each intended subcontractor must be given when submitting the tender.
Each subcontractor used must meet the same suitability criteria as the primary contractor. Suitable proof for each subcontractor must be submitted.
The subcontractor must also submit
- A declaration of availability (see Declaration of availability preprinted form) together with the request to participate/tender. - FAIR preprinted form"
- 14. Russia sanctions - Declaration on Regulation (EU) 833/2014 (To be submitted with the tender by means of self-declaration): On 08.04.2022, the Council of the European Union adopted Regulation (EU) 2022/576 amending Regulation (EU) No 833/2014 concerning restrictive measures in view of Russia's actions destabilising the situation in Ukraine. This entered into force on 09.04.2022. As a regulation, it has direct legal effect in the member states and has a direct impact on the award of public contracts and concessions.
- Compliance with data protection (To be submitted with the tender by means of self-declaration): Declaration of comliance with data protection requirements on preprinted form.
Abschnitt IV: Verfahren
Darmstadt
Abschnitt VI: Weitere Angaben
Evaluation Method for the offers is based on the price-quotient method:
Total Bid Offer: 30 %
Performance Criteria: 70 %
Criteria (100%):
Bidders must prove that all parameters and tolerances given within the specification are 100% fulfilled. This can be submitted as a datasheet. If tolerances are specified, offers, which reach the best value, are rated more positive. Offers, which do not prove and match every parameter or show parameters outside tolerances, will be excluded.
The evaluation description is found in detail within the document, Special-Application-Requirements.
other Supporting documents:
- Bidding consortium (To be submitted with the tender by means of self-declaration): BGB company with joint and several liability with listing of all members and their authorised representatives incl. naming of an authorised representative who shall represent the consortium in a legally binding manner vis-à-vis the Contracting authority. The tender must be accompanied by a legally binding declaration signed by all joint members that the lead firm, as authorised representative, represents the joint members listed before the Contracting authority and is jointly and severally liable, having an effect on each member, for performing the service in accordance with the contract.
Bekanntmachungs-ID: CXS0YYEYRWV
Postanschrift:[gelöscht]
Ort: Bonn
Postleitzahl: 53123
Land: Deutschland
The competent reviewing authority is
Federal Public Procurement Tribunal
Villemombler Straße 76
53123 Bonn
Tel.: 0228 9499-0
Fax: 02[gelöscht]
Email: [gelöscht]
Website: http://www.bundeskartellamt.de
Candidate/ Bidder is requested to clearly identify those sections of the tender that contain a trade or business secret. If Bidder fails to do so, the Public Procurement Tribunal may, in the case of a review procedure, assume that Bidder has agreed to have these documents inspected (§165 para. 3 GWB). As Awarding Authority, FAIR is obliged to make the tender file available to the Public Procurement Tribunal immediately when initiating a review procedure (§ 163 para. 2 cl. 3 GWB).
Candidates/ Bidders have a right to expect the contracting authority's compliance with the Bidder-protecting provisions re: the tender procedure (§ 97 para. 6 GWB). If Candidate/ Bidder interested in the contract considers that Bidder's rights have been infringed through failure to comply with award regulations, the infringement must be reported to FAIR within ten calendar days (§ 160 para. 3 cl. 1 no. 1 GWB).
Infringements identifiable on the basis of the announcement or the award documents must be asserted against FAIR within the deadline for submission of ten-ders specified in the announcement (§ 160 para. 3 cl. 1 nr. 2 - 3 GWB).
If FAIR informs Candidate/ Bidder that FAIR is unwilling to redress its complaint, it is possible to file an appeal for review with the aforementioned Public Procurement Tribunal within 15 days of receipt of the notification (§ 160 para. 3 cl. 1 no. 4 GWB).
Bidders whose tenders are not to be considered for the award will be informed prior to the award according to § 134 GWB. A contract may only be concluded 15 calendar days after this information has been sent by FAIR. In the case of trans-mission by fax or electronic means, this period shall be ten calendar days. It commences on the day after dispatch of the information by FAIR. After this period has expired, a surcharge is possible, even if the deadline is not passed according to § 160 para. 3 GWB. An application for review would therefore have to be delivered to FAIR by the Public Procurement Tribunal before the expiry of the deadline according to § 134 GWB in order to prevent a surcharge.
According to § 135 para. 1 and 2 GWB, the ineffectiveness of a commission can only be established if it has been asserted in the review procedure within 30 calendar days of the conclusion of the contract but not later than six months after the conclusion of the contract. If the contracting entity has published the award in Official Journal of the European Union, the period unenforceability shall end 30 calendar days after announce-ment of the publication of the award in the Official Journal of the European Union.