81265077-1,000 Islands — Renewable Energy for Electrification Programme Phase 2 (REEP2) Referenznummer der Bekanntmachung: 81265077
Bekanntmachung vergebener Aufträge
Ergebnisse des Vergabeverfahrens
Dienstleistungen
Abschnitt I: Öffentlicher Auftraggeber
Postanschrift:[gelöscht]
Ort: Eschborn
NUTS-Code: DE71A Main-Taunus-Kreis
Postleitzahl: 65760
Land: Deutschland
E-Mail: [removed]
Telefon: [removed]
Fax: [removed]
Internet-Adresse(n):
Hauptadresse: https://www.giz.de
Abschnitt II: Gegenstand
81265077-1,000 Islands — Renewable Energy for Electrification Programme Phase 2 (REEP2)
Indonesia's demand for electricity is increasing steadily. The island nation has great renewable energy (RE) potential, especially in the decentralised area with solar photovoltaics (PV), bioenergy, hydropower, but also wind power.
The National Energy Plan (RUEN) specifies the strategy for the energy sector, including a target share of RE in the electricity mix of 23 % for 2025. Currently the RE share stagnates at around 13 % in the power mix. Despite the high technical and economic potential, solar and wind energy as well as electricity generation from biomass only play a subordinate role. The political targets for the expansion of decentralised RE are only insufficiently integrated in the 10-year power expansion plan (RUPTL). The regulatory framework for decentralised RE is insufficient.
Achieving the national climate protection goals (NDC) is inextricably linked to the decarbonisation of the electricity sector. At this stage, the capacities of state and private-sector actors as well as the regulatory and technical framework conditions for promoting decentralized RE are still too weak.
To address these challenges, the REEP2 programme has been devised, building upon REEP phase 1, with the following objective: ‘The institutional, regulatory and technical conditions for achieving the policy target of 23 % of renewable energy in the energy mix in 2025 have been improved at national and regional level.’
GIZ REEP 2 De RITZ -Jl. HOS. Cokroaminoto No 91, RT.3/RW.5, Menteng, Kec. Menteng, Kota Jakarta Pusat, Daerah Khusus Ibukota 10310 Jkarta, INDONESIA.
Outputs
In accordance with the current challenges in the RE sector, the Project combines a top-down and bottom-up approach in its institutional change strategy.
— Output 1 aims to improve the institutional capacities and personal competencies of the national General Directorate for Electricity (DJK) and the national General Directorate for New and Renewable Energies and Energy Conservation (EBTKE) to regulate the RE sector at the central government level;
— Output 2 aims to improve the capacities of the national electricity supply company PLN at national and regional level in the three target regions (Sulawesi, Bangka-Belitung, and NTT). For this purpose, the technical skills of the employees in the areas of RE-optimized power system planning and operation with a high proportion of variable RE are strengthened;
— Output 3 aims to promote the expansion of RE by introducing the previously unused concept of load shifting, especially in small island grids, through private sector participation.
Executing agencies and partner structure
The political partner is the General Directorate for New and Renewable Energies and Energy Conservation (Directorate Jenderal Energie Baru Terbarukan dan Konservasi Energi, EBTKE). The General Directorate for Electricity (Directorate Jenderal Ketenagalistrikan, DJK) plays a key role as it is responsible for the formulation of the national strategy in the field of electricity. The state-owned power supply company (PT. Perusahan Listrik Negara, PLN) also occupies a key position as it develops the annually released 10-year power expansion plans.
Target groups and regions
The target group are Indonesia's electricity consumers who benefit from the country's reliable, cost-efficient and sustainable power supply. Other important stakeholders are experts and managers in public and private-sector organisations, REEP2 will target grids from very small (up to 0.5 MW peak load) up to large grids (more than 1000 MW peak load) in three regions:
— in this larger grid category, the two grids of North and South Sulawesi (peak load about 1500 MW) will act as target grids;
— with regards to medium-sized grids, the two main islands Bangka and Belitung will remain two target grids;
— the remaining 7 islands of Bangka-Belitung region belong to the very small gird classification (less than 0.5 MW peak load). Besides Bangka-Belitung, small to medium sized grids will be targeted in the Nusa Tengara Timor (NTT) region which consists of the main island Timor, Flores and Sumba as well as surrounding islands.
It is possible to continue key elements of the service specified in the tender as part of a follow-on measure within the context of the basic project, up to additional 36 months, if the project term is extended by the commissioning parties of GIZ.
Within the framework of the basic project described in the terms of reference, GIZ reserves the right to award contracts for additional services of this type up to an extent of additional EUR 1 000 000, to the successful company in this procedure by means of a negotiated procedure without a prior call for competition, or to enter into a follow-on contract pursuant to the criteria listed in the terms of reference and the contract. All relevant remuneration items shall be increased proportionately. Moreover, changing framework conditions in Indonesia might create window of opportunities to support the political partner in their mission, if this is the case also additional services up to the mentioned extent can be awarded. Precondition for this option is that additional funding is made available by the commissioning parties of GIZ.
Abschnitt IV: Verfahren
Abschnitt V: Auftragsvergabe
Auftragsvergabe Energynautics GmbH
Postanschrift:[gelöscht]
Ort: Darmstadt
NUTS-Code: DE711 Darmstadt, Kreisfreie Stadt
Postleitzahl: 64293
Land: Deutschland
E-Mail: [removed]
Telefon: [removed]
Fax: [removed]
Internet-Adresse: http://energynautics.com
Abschnitt VI: Weitere Angaben
Notices-ID: CXTRYY6YLHN
Postanschrift:[gelöscht]
Ort: Bonn
Postleitzahl: 53123
Land: Deutschland
E-Mail: [removed]
Telefon: [removed]
Fax: [removed]
Internet-Adresse: https://www.bundeskartellamt.de
According to Article 160, Section 3 of the German Act Against Restraint of Competition (GWB), application for review is not permissible insofar as
1) The applicant has identified the claimed infringement of the procurement rules before submitting the application for review and has not submitted a complaint to the contracting authority within a period of 10 calendar days; the expiry of the period pursuant to Article 134, Section 2 remains unaffected;
2) Complaints of infringements of procurement rules that are evident in the tender notice are not submitted to the contracting authority at the latest by the expiry of the deadline for the application or by the deadline for the submission of bids, specified in the tender notice;
3) Complaints of infringements of procurement rules that first become evident in the tender documents are not submitted to the contracting authority at the latest by the expiry of the deadline for application or by the deadline for the submission of bids;
4) Mmore than 15 calendar days have expired since receipt of notification from the contracting authority that it is unwilling to redress the complaint.
Sentence 1 does not apply in the case of an application to determine the invalidity of the contract in accordance with Article 135, Section 1 (2). Article 134, Section 1, Sentence 2 remains unaffected.