Framework Agreement Cable Monitoring Systems
Auftragsbekanntmachung – Sektoren
Lieferauftrag
Abschnitt I: Auftraggeber
Postanschrift:[gelöscht]
Ort: Berlin
NUTS-Code: DE3 Berlin
Postleitzahl: 10557
Land: Deutschland
E-Mail: [gelöscht]
Internet-Adresse(n):
Hauptadresse: www.50hertz.com
Abschnitt II: Gegenstand
Framework Agreement Cable Monitoring Systems
The general scope of this tender is the supply, delivery, installation, tuning, on-site testing, commissioning, service and maintenance of cable monitoring systems.
Framework Agreement DAS cable/OHL
The Service includes the supply, delivery, installation, tuning, on-site testing, commissioning, service and maintenance of DAS for cables and overhead lines (OHL).
estimated value: 64 units
maximum value: 120 units
Extension option 3 x 1 year
Based on technical information with references and HSE information for the purpose of ranking only.
Details on Evaluation can be found in the Prequalification Questionnaire.
INEA/CEF/ENER/M2017/1509932
Framework Agreement DTS&RTTR cable
The Service includes the supply, delivery, installation, tuning, on-site testing, commissioning, service and maintenance of DTS&RTTR for cables.
estimated value: 72 units
maximum value: 140 units
Extension option 3 x 1 year
Based on technical information with references and HSE information for the purpose of ranking only.
Details on Evaluation can be found in the Prequalification Questionnaire.
INEA/CEF/ENER/M2017/1509932
Framework Agreement DTS&RTTR OHL
The Service includes the supply, delivery, installation, tuning, on-site testing, commissioning, service and maintenance of DTS&RTTR for overhead lines (OHL).
estimated value: 10 units
maximum value: 20 units
Extension option 3 x 1 year
Based on technical information with references and HSE information for the purpose of ranking only.
Details on Evaluation can be found in the Prequalification Questionnaire.
INEA/CEF/ENER/M2017/1509932
Framework Agreement ocfl
The Service includes the supply, delivery, installation, tuning, on-site testing, commissioning, service and maintenance of ocfl (online cable fault location).
estimated value: 12 units
maximum value: 24 units
Extension option 3 x 1 year
Based on technical information with references and HSE information for the purpose of ranking only.
Details on Evaluation can be found in the Prequalification Questionnaire.
INEA/CEF/ENER/M2017/1509932
Framework Agreement sabotage/moisture
The Service includes the supply, delivery, installation, tuning, on-site testing, commissioning, service and maintenance of sabotage/moisture monitoring systems.
estimated value: 24 units (12/12)
maximum value: 48 units
Extension option 3 x 1 year
Based on technical information with references and HSE information for the purpose of ranking only.
Details on Evaluation can be found in the Prequalification Questionnaire.
INEA/CEF/ENER/M2017/1509932
Abschnitt III: Rechtliche, wirtschaftliche, finanzielle und technische Angaben
Signed Candidate Selection Questionnaire
=====
Exclusion grounds according §§ 123, 124 GWB: Confirmation that there are no grounds for exclusion pursuant
to §§ 123, 124 GWB with regard to our company and, if applicable, those from whom the suitability is borrowed.
=====
Minimum wages: confirmation that paid wages are compliant with the statutory minimum wage or collectively
agreed remuneration regulations are obeyed, where applicable.
=====
Financial Report: submission of a financial report dated of maximum 6 months from the submission deadline
from an independent credit rating company (Credit Safe, Dun and Bradstreet, Graydon or equivalent).
=====
Annual reports: submission of annual reports or annual financial statement, or alternatively balance sheets
(to be justified) or, in the extreme alternative, a profit and loss account (to be justified) for the last two financial
years. If the applying company exists less than 2 years please provide the respective turnover data and financial
documents for the period for which it is available.
=====
Business insurance: submission of certificate
=====
Languages: Confirmation that during the whole time of the order-execution a German speaking contact person
(Language Requirements German B2) is available for technical and logistical problems.
All of the above.
Representative references for the supply of cable monitoring systems: The requested
information, minimum criteria and scoring system are explained in the excel files "Evaluation of References" and they are different per lot:
=====
Complete cable monitoring system: confirmation that the candidate can provide a complete cable monitoring system.
=====
Agreement on Audit: Acceptance of audit in case of doubts related to the information provided with this
application.
=====
ISO 9001 or equivalent: submission of certificate
=====
ISO 14001 or equivalent: submission of certificate
=====
ISO/IEC 27001 or equivalent: submission of certificate
=====
ISO 45001 or equivalent: submission of certificate
All of the above, except ISO 9001, ISO 14001, ISO/IEC 27001, ISO 45001
The applicant must request, complete and submit by the closing date (see IV.2.2.) the Candidate Selection
Questionnaire with the requested data and documents.
In order to have full access to the tender documents, the applicant must provide the NDA.
In parallel, the applicants that have not registered in the tendering platform Ariba, must request the access to
Ariba, by sending an e-mail to the responsible buyer (see I.1.) mentioning the name of the legal entity, address,
VAT number, name + e-mail + telephone of the contact(s).
Information to access the tender on the Ariba platform will be provided by e-mail as soon as possible.
General explanations of the content of the application to participate: to be found under VI.3).
Abschnitt IV: Verfahren
Abschnitt VI: Weitere Angaben
(a) Q&A:
Interested companies can contact the awarding authority with questions about the application at least 7 days before the end of the participation period (Stage 1). If the questions or answers are of general interest, they will be made available in anonymized form. All interested companies or applicants are obliged to take note of the questions and answers published when drafting their application to participate. Failure to do so may result in exclusion from the procedure.
Deadlines for questions regarding the offer period will be clarified within the tender documents.
(b) Tender documents:
For reasons of confidentiality, selected parts of the tender documents are only made available to the applicants within the application procedure after a confidentiality declaration has been issued (cf. Art. 73(1), fourth subparagraph, in conjunction with Art. 39(2) of Directive 2014/25/EU). This does not apply if a company has no legitimate interest in the confidential documents being made available, in particular if they are manifestly unsuitable.
(c) Continuation of point III.1.4) Objective participation rules and criteria:
General explanations on the content of the request to participate.
1) Current means not older than 6 months backdated from the date of the end of the participation period.
2) If an applicant cannot present a third party certificate, e.g. an entry in the register, as required, a comparable third party certificate must be presented and the comparability must be demonstrated by appropriate explanations.
3) Foreign applicants: as a rule, they must submit the required declarations/evidence in German or English or in an officially certified translation. If a declaration/evidence cannot be submitted at all, the reasons for this must be given, a comparable declaration/evidence must be submitted and an explanation must be given in German or English why the comparability exists.
4) Consortia of applicants. Together with the application for participation, a legally binding declaration of participation, signed and completed in full by all members has to be submitted. Particular attention shall be paid to the aspect of compliance of the formation of the applicant group with cartel law. Each member of the applicant group must submit the declarations and evidence required under III.1.1) and II.1.2). This applies to a limited extent to the declarations and evidence under III.1.3) if the applicant group foresees a division of tasks and if, for example, certain references can only be submitted by one applicant group member; any limited submission of declarations and evidence must be explained in detail by the applicant group in an Annex to the applicant group declaration. The same rules apply to applicant groups as for applicants.
5) Other companies: applicants can use other companies to prove their suitability (suitability loan). In this case, the other company must submit a declaration of commitment according to which it will provide a specifically defined partial service for the applicant in the event of an order. Companies which lend the suitability to the applicant (suitability lenders and subcontractors) must be summarised in a list in which the name and registered office of the other company and the part of the service are formulated.
(d) Besides 50Hertz Transmission GmbH all companies affiliated with the Elia Group (in particular 50Hertz Offshore GmbH and Elia Grid International GmbH) are entitled to call on this framework agreement.
(e) The first offer can only be evaluated if its valid, complete, unconditional and eligible, meets the technical conditions of the attached enquiry documents, is fully completed in all parts as an individual offer and is received by us in accordance with the deadlines set out in the invitation to tender. The bidders have no right for
negotiation.
Postanschrift:[gelöscht]
Ort: Berlin
Postleitzahl: 10825
Land: Deutschland
E-Mail: [gelöscht]
Telefon: [gelöscht]
Fax: [gelöscht]
Internet-Adresse: http://www.berlin.de/sen/wirtschaft/wirtschaft-und-technologie/wirtschaftsrecht/vergabekammer/
The application for review proceedings before the public procurement tribunal is inadmissible if:
1) The applicant became aware of the claimed violation of public procurement provisions before filing the application for review, but did not complain to the contracting authority within a time limit of 10 calendar days; the expiry of the time limit under § 134(2) remains unaffected;
2) Violations of public procurement provisions which become apparent from the tender notice are not notified to the contracting authority by the end of the time limit for the application or the submission of a tender specified in the notice
3) Violations of public procurement provisions which only become apparent from the procurement documents are not notified to the contracting authority by the end of the time limit for the application or the submission of a tender specified in the notice;
4) More than 15 calendar days have expired since receipt of notification from the contracting authority that it is unwilling to redress the objection.
Sentence 1 shall not apply to an application under § 135(1) No 2 to have the contract declared ineffective. § 134(1) sentence 2 shall remain unaffected.